What is the regulatory process and predicted timeline?

Once NuScale submits the Design Certification Application in late 2016, the goal is for the NRC to deliver a review and approval of that design in about 40 months. UAMPS will also have to submit a license application and complete an Environmental Impact Statement for the proposed location. The approval process for both of those documents is expected to require approximately 36 to 48 months to complete.